SCHWARZE PUMPE SETTLING TANK

Task: Empty and dismantle a 10,000 m³ settling tank
Time frame: September 1997 to September 1998
Substances: 3,500 m³ tar oil mixture; 3,000 m³ phenolic wastewater

Porenbetonmehl

Schwarze Pumpe settling tank

Corrosion and structural weakness demanded the emptying, cleaning, and dismantling of settling tank "2.112" at the Schwarze Pumpe site. Volatilisation of the lighter constituents existed; pyrophorous substances could activate and self-ignite. This fact made it impossible to simply cut the tank into sections for dismantling.

  • Anheben des Tankdeckels
  • Verschrottung des Tanks

Information

At the start of the project, the tank contained a mixture of phenolic waste water and tar oil so-lids. The phenolic water was drained off through outlet pipes near the top before the mixture was heated. A combination pump/heat-exchanger apparatus then heated the tank contents. Materials were removed from the tank through outlet pipes at the base. This procedure sub-stantially reduced the inherent danger of the operation.

Coordinating closely with the local mining authorities, a 500-ton crane was used to lift the top from the tank. Excavators removed the remaining contents of the tank. Cleaning and disas-sembly of the structure prepared it for scrap.

HAVE YOU ALREADY HEARD?

If you're in Germany, then there's a Lobbe representative close to you. For more information about our locations.

OIL-ALARM

24 hour hotline 0 180 5 - 600 500 (from Germany)

QUICK CONTACT

Still have questions? We'd be glad to talk with you personally. To our contact page